Construction update - week commencing 17 May 2021

Foundations/Groundwork

  • We will be pouring the second section of the fifth-floor slab on Tuesday 18 May.
  • Scaffolding will commence from Tuesday 18 May.
  • The parapet walls for the fourth-floor roof are complete. A parapet is a low protective wall along the edge of a roof, bridge, or balcony.
  • We will continue to erect columns from the fifth floor to the roof level. They will then be poured with concrete shortly after they have been erected.
  • Decking to the roof level will commence for most of next week. Decking is the temporary support framework that’s set out prior to concrete pouring.
  • The drainage and services along the Dorset Road elevation will continue next week.
  • Various deliveries will be arriving through-out the week.
  • We will currently not be working on Saturdays however notice will be given if future Saturdays are required.

Decking to Fifth Floor

Progression to Concrete Structure