South Lambeth construction update - For week starting 8th February

Each week Hill Partners, the contractor who is building 'Block A' for Homes for Lambeth, publishes update on what will happen on site.

This update can be found on the hoarding on the entrance to Wimborne House. This weeks update is also shown below.

WEEKLY UPDATE
For week commencing 8th February 2021

  • Foundations/Groundwork.
  • Excavating of pile caps ongoing
  • Removal of concrete from top of pile caps by the cropping method
  • Integrity testing of piles ongoing
  • Installation of ground beams
  • Concrete blinding to formation level
  • Installation of Cellcore board underneath the concrete slabs
  • Commencement of Ground floor slab rebar

Frequently asked questions

In response to several questions and queries, we have put together a general Q & A document. You can see this by clicking here.

If there are further questions please contact Maxine, Homes for Lambeth Resident Engagement Officer via:

Tel: 07588 561 771

Email: [email protected]

Resident Engagement Panel

The role of the Resident Engagement Panel (REP) is to represent the interests of tenants and homeowners affected by the rebuilding proposals.

It is not a decision-making body but is expected to make recommendations to Homes for Lambeth relating to rebuild proposals. If you would like to join the REP, or just find out more please contact Maxine, Homes for Lambeth Resident Engagement Officer via:

Tel: 07588 561 771

Email: [email protected]

Created with NationBuilder