WEEKLY UPDATE - For week commencing 22nd February 2021
Foundations/Groundwork.
- Excavating of pile caps ongoing
- Removal of concrete and muck away from pile caps ongoing
- Integrity testing of piles ongoing
- Installation of ground beams ongoing
- Installation of drainage ongoing
- Concrete blinding to formation level ongoing
- Installation of Cellcore board ongoing
- Commencement of Ground floor slab rebar ongoing
- Concreting ground floor slab. Pour 1 of 3
- Installation of District heating and underground services phase 2 of 3 ongoing
- Tower Crane being installed on Thursday 25th for 2 days (separate letters being sent out)